Why Tunde Idiagbon Flyover Project Is Delayed – Kwara Govt
Kwara State government has attributed the delay in the completion of Tunde Idiagbon Flyover project on University of Ilorin (UNILORIN) Road, Tanke, Ilorin, the state capital to market forces and climatic challenges.
The commissioner for works, Engr Rotimi Ilyasu, who spoke on the project, said the delay in the project completion, which was started over a year ago, was due to weather challenges and market forces.
He said that work on the flyover project has reached between 85 and 90 percent completion.
He, however, said that weather conditions had slowed down the rate of work, explaining that recent rainfalls had washed away earth work on surfaces of the road.
“In a couple of weeks, hopefully before May 29, it will be ready for use. Actually, both sides of the flyover are partially open for motorists now, especially in the evening when work is not done. All hands are on deck to deliver a quality job. This is a project we can't take chances on. And so far, it's been very good,” he added.
He identified weather challenges and undulating market prices as some of the factors responsible for the delay in delivering the project to the public.
But, the residents of the area have lamented the inconvenience the delay of the project has caused them.
Those who spoke with LEADERSHIP Friday included commuters and shop owners on the project route.
Two residents, Mr John Abidemi and Olagoke Kolade, however, expressed appreciation to the state government for embarking on the project aimed at easing traffic gridlock on the ever-busy Tanke Road.
They said, “This area used to witness heavy traffic jams. With this, we can see that achievements are speaking for the governor among his peers in the All Progressives Congress (APC).
“However, we residents of the Tanke area feel that the project should have been completed by now knowing that this project has a deadline. This is the rainy season and we're yet to get the project completed. We only hope that the project will be delivered for the use of the general public.”
They called on the government to complete the project on time to ease the inconveniences being experienced.
Mrs Opemipo Shade, who said that development does not come to any society without some level of suffering or hardship, however, said that some people were being deprived of their socio-economic livelihood along the route.
“So, we call on the state to expedite action on the project and commission it for the use of the people, especially the students, and motoring public,” she stated.
Cloud Tag: What's trending
Click on a word/phrase to read more about it.
Dar-Al-Handasah Consultants Ltd Flights To Ilorin ASMAU PLAZA Matthew Babaoye Alore Razak Atunwa Ope Saraki Oniwasi Agbaye Joseph Alex Offorjama Umar Danladi Shero Code Of Conduct Bureau UITH Yinka Aluko Abdulkadir Remi Hawawu Kawu Baraje Lotus Bank UTME Talaka Parapo Niguel Gallando Marcias Salihu Ajibola Ajia Yekeen Alabi Sheriff Olanrewaju Agor Moses Rahman Popoola Folaranmi Aro Isaac Aderemi Kolawole Muhammed Aliyu Wahab Abayawo Mohammed Halidu FOMWAN Olabode George Towoju Amos Bajeh GAMA International Aviation College March 18 Egbejila Abubakar Kawu Baraje Raimi Iyanda Kwara State Geographic Information Service IF-K Isau Olabimpe Olani Raliat Elelu-Habeeb Fulani Kwara Poly Bibire Ajape Ibrahim Oniye Fatai Olodo Offa Grammer School Muhammad-Mustapha Suleiman Yakubu Mohammed Abdullahi Adegoke Bamidele Umar Saro Babatunde Ajeigbe Aminat Ahmed Saad Omo Iya Assayomo Muslim Media Watch Group Of Nigeria Oba Abdulkadir La\'aro Tope Daramola Plat Technologies GGDSS Pakata NIPOGA Charcoal JMK Construction Company Limited Zaratu Umar Ijagbo Health Centre Olota Of Odo-Owa Baba-Isale Convocation Ceremonies Jide Ashonibare Olatunde Michaels Mahmud Durosinlohun Atiku Bamidele Adegoke 20 Billion Bond NITDA Adeola Abraham