Why Tunde Idiagbon Flyover Project Is Delayed – Kwara Govt
Kwara State government has attributed the delay in the completion of Tunde Idiagbon Flyover project on University of Ilorin (UNILORIN) Road, Tanke, Ilorin, the state capital to market forces and climatic challenges.
The commissioner for works, Engr Rotimi Ilyasu, who spoke on the project, said the delay in the project completion, which was started over a year ago, was due to weather challenges and market forces.
He said that work on the flyover project has reached between 85 and 90 percent completion.
He, however, said that weather conditions had slowed down the rate of work, explaining that recent rainfalls had washed away earth work on surfaces of the road.
“In a couple of weeks, hopefully before May 29, it will be ready for use. Actually, both sides of the flyover are partially open for motorists now, especially in the evening when work is not done. All hands are on deck to deliver a quality job. This is a project we can't take chances on. And so far, it's been very good,” he added.
He identified weather challenges and undulating market prices as some of the factors responsible for the delay in delivering the project to the public.
But, the residents of the area have lamented the inconvenience the delay of the project has caused them.
Those who spoke with LEADERSHIP Friday included commuters and shop owners on the project route.
Two residents, Mr John Abidemi and Olagoke Kolade, however, expressed appreciation to the state government for embarking on the project aimed at easing traffic gridlock on the ever-busy Tanke Road.
They said, “This area used to witness heavy traffic jams. With this, we can see that achievements are speaking for the governor among his peers in the All Progressives Congress (APC).
“However, we residents of the Tanke area feel that the project should have been completed by now knowing that this project has a deadline. This is the rainy season and we're yet to get the project completed. We only hope that the project will be delivered for the use of the general public.”
They called on the government to complete the project on time to ease the inconveniences being experienced.
Mrs Opemipo Shade, who said that development does not come to any society without some level of suffering or hardship, however, said that some people were being deprived of their socio-economic livelihood along the route.
“So, we call on the state to expedite action on the project and commission it for the use of the people, especially the students, and motoring public,” she stated.
Cloud Tag: What's trending
Click on a word/phrase to read more about it.
Saraki Age AbdulKareem Saka Adeyemo Baba Isale Young Progressives Party Abubakar Ndakene Memunat Monsuma NIPOGA Sayomi Olubukola Kifayat Adedeji Hamidat Sulyman-Yusuf Hussein Oloyede Salman Suleiman Mamman Saba Jibril Najim Yaasin Shehu Raheem Adaramaja Balogun-Ojomu Adebayo Salami Binta Abubakar-Mora Oko Erin National Information Technology Development Agency Mansurat Amuda-Kannike Abdul Jimoh Mohammed Saka Balikis Kehinde Shonga Farm Project Susan Modupe Oluwole Olomu A.E. Afolabi Baboko Chemiroy Nigeria Limited Elerin Of Adanla Irese Ebola Oke Sunna Falokun-Oja Abdulrasheed Akogun Zubair Folorunsho Erubu Agbarere Saka Aleshinloye Ali Ahmad Saduki Lafiagi Moses Adekanye Owo Isowo ASKOMP Ilofa Bolaji Nagode Moses Rahman Popoola Omupo Towoju Afonja Abdulkadir Akanbi-Oke Abubakar Baba Sulaiman Abdulkadir Remi Hawawu Kannike Dele Belgore Abubakar Bature Sulu-Gambari A.G.F Abdulrasaq Ubandoma Of Ilorin Adegoke Bamidele Sulu Babaita Isiaka Admiralty Villa International Public Sector Accounting Standards Wakilin Mata Lafiagi Centre For Peace And Strategic Studies Hassan Oyeleke Lithium Deposit Gobirawa Temitope Ogunbanke Oni Adebayo TESCOM 2017 Budget Afolayan Ayoade Akinnibosun Sa\'ad Alanamu Shonga Adaramaja Ilorin South Constituency Onilu